A Critical Step With Floors Over Unheated Space

A few times in the last year, our inspectors have run into a critical oversight that’s caused problems: incorrect placement of vapour barrier in floors over an unheated space.

First off, there’s a general rule on where vapour barrier goes: the warm side of the building. For things like walls and ceilings, that’s a really obvious thing. However, when building a stud floor over, say, an unheated crawl space – which is usually insulated later in the build than other sections – it’s easy to overlook the vapour barrier placement.

This image shows the correct location of vapour barrier in a floor over an unheated space.

The image provided here illustrates how it should be done: vapour barrier is drawn over the joists before the sheathing goes down.

What some folks might overlook is the vapour barrier when building a suite over a heated garage. Garages are considered unconditioned (unheated) spaces, and for good reason: they’re often exposed to serious drops in temperatures, even if insulated and heated like the rest of the house. Further, garages must have a layer of vapour barrier encapsulating them to keep vehicle fumes away from the rest of the house. In this case, the old rule – vapour barrier on the warm side – holds true.

There is one critical exception: if closed-cell foam is used as the insulation. In that case, the foam serves as the vapour barrier, and can be applied on the underside of a sheathed floor without vapour barrier being in place.



Southwest New Brunswick Service Commission

SNBSC is an independent organization, enacted by provincial legislation that provides regional services to municipalities and the rural district. The organization is governed by a Board of Directors comprised of the mayors of all the municipalities within the region and a representative of the rural district.